ENERGY AUDIT SCHEME FOR INDUSTRIES
ENERGY AUDIT SCHEME - DOWNLOAD
1
|
Name of the scheme
|
Energy Audit Scheme
|
|
Important Instructions
|
- All micro, small and medium unit existing anywhere in State of Haryana shall be eligible provided, if the energy audit has been done by an Energy Auditor certified by the Bureau of Energy Efficiency (BEE).
- Investment in new plant & machinery and equipments focussed towards enhancing energy efficiency shall only be eligible.
- Large units are not eligible.
- The items of manufacture should not fall in the restrictive list as notified by State Government from time to time.
- CLU/NOC is required from competent authority, if applicable.
- The unit should be in regular production at the time of disbursement of assistance.
- In case of rejection of case, an appeal shall lie with the Principal Secretary, Industries within a period of 30 days.
|
|
Documents to be enclosed with the request
|
- Ack. EM part-II/UAM Registration.
- Certificate of Incorporation/ Partnership deed.
- Board resolution/ Power of attorney
- Change of Land Use (CLU)/ NOC from competent authority, if applicable.
- Copy of first sale bill.
- Copy of Energy audit certification.
- CA certificate of Expenditure (in original) giving the details ( as per prescribed format)
- Copy of the bills raised by certifying agency and proof of payment thereof.
- Audited balance sheet of the unit of last year
|
|
Timeline and Procedure
|
- Submit application online with all the required documents within 03 months from the date of completion of energy audit/purchase of capital equipments.
- Online application submitted shall be processed and examined by concerned Joint Director/ Deputy Director.
- If any discrepancy is found, the application shall be put onhold and be communicated to the applicant within 10 working days.
- The applicant will rectify the deficiencies within 06 weeks failing which the application will liable to be rejected.
- After completion of the application, the approval letter will be issued within 60 working days.
- The applicant will submit the documents mentioned in approval letter within 15 days.
- After compliance of conditions of approval letter, the sanction letter for releasing the incentive will be issued within 15 working days.
|